را SNHT hoist trolley adopts a mechatronic design. By replacing different molds, wire ropes of different specifications can be pressed, making it easy to control. Electric wire rope hoists are widely used, but there are fewer people who can operate them correctly. Next, we will introduce how to use the SNHT hoist trolley correctly.

The newly installed 5 ton electric hoist should first be tested empty for several times. However, do not turn on the power before the installation is completed.

 

Before normal use, a 10-minute static load test should be carried out at 125% of the rated load and lifted about 100 mm from the ground to check whether it is normal.

 

During installation, commissioning and maintenance, it is necessary to strictly check whether the limit device is flexible and reliable. When the hook is raised to the upper limit position, the distance from the hook shell to the drum shell must be greater than 50mm.

 

را electric wire rope hoist should be operated by a dedicated person, and the operator should fully understand the safe operating procedures. It is strictly forbidden to pull or lift at an angle.

 

During use, specialized personnel must regularly inspect the 5 ton electric hoist, take timely measures if any faults are found, and record them carefully.

 

When using the electric wire rope hoist, you must maintain sufficient lubricating oil and keep the lubricating oil clean and free from impurities and dirt.

 

If a fault is found, the main power supply should be cut off immediately. After use, the power supply should be cut off immediately.

The purpose of maintenance is to prevent and reduce the occurrence of failures, prolong the maintenance cycle, maintain good technical condition and play the best benefit. Proper operation and maintenance can extend the service life of the SNHT hoist trolley. It can also protect the safety of the operator during operation.